Sulzer GmbH
High-Quality IT Services from A to Z
Sulzer GmbH has been providing IT consulting and future-ready solutions for complex industrial IT environments since 1978. With over 700 experts worldwide, the company supports businesses end to end in their digital transformations – from business analysis and data & AI to software development and IT infrastructure, as well as SAP and Infor transformations.
Since 2018, Sulzer has been strategically using artificial intelligence to optimize processes, improve data quality, and support well-informed decision-making. Sulzer stands for tailored solutions that integrate into existing processes and IT landscapes and deliver lasting value in day-to-day operations.
Sulzer’s Challenge
Resource Planning Without Real-Time Visibility
To manage its complex projectProjectA project is a time-limited undertaking with defined objectives and resources that delivers unique results and often includes complex tasks. business, Sulzer GmbH needs an up-to-date view of resource utilization. Information about which resourcesResourceResources are all the people, places and things that you need to complete projects. The most important resource? Employees, of course! are assigned to which projects, at what capacity, and for what period of time must be available at all times and accessible with as little effort as possible.
In practice, however, this requirement ran up against the limits of historically established structures. Over the years, Excel had become the solution for resource and capacity managementCapacity ManagementSynonym for → Capacity PlanningCapacity planning and management refers to the process of matching the “capacity supply” (employees, resources, skills, etc.) with the “capacity demands” (projects) of an organization. It is considered a part…. The resulting manual administration created several challenges in daily practice:
- Lack of transparency: Data was collected separately from day-to-day operations and therefore was not available until after the month-end closing. As a result, there was no reliable insight into current employee utilization, making proactive management impossible.
- High maintenance effort: Several employees were occupied with consolidating data, correcting errors, and filling in missing information.
- High risk of errors: The manual process was not only time-consuming, but also prone to data-entry errors.
Would you like to display the content of YouTube? Then please confirm this with one of the two buttons. Please note that data will be exchanged with a third-party provider.
More InformationThe Interviewees
Dr. Caroline Sauter and Markus Köster explain how Sulzer GmbH made the transition to proactive resource planning and the role Meisterplan played in that transformation.
Markus Köster
Responsible for managing all projects, ensuring their profitability, and overseeing resource utilization at the department level.
Dr. Caroline Sauter
Responsible for successful project delivery, optimal staffing, and employee utilization, as well as the involvement of external partners.
Sulzer’s Solution
Up-to-Date Resource Planning with Meisterplan
Sulzer GmbH selected Meisterplan as its central tool for resourceResourceResources are all the people, places and things that you need to complete projects. The most important resource? Employees, of course! and capacity managementCapacity ManagementSynonym for → Capacity PlanningCapacity planning and management refers to the process of matching the “capacity supply” (employees, resources, skills, etc.) with the “capacity demands” (projects) of an organization. It is considered a part… in order to reduce administrative effort and create greater transparency across its projectProjectA project is a time-limited undertaking with defined objectives and resources that delivers unique results and often includes complex tasks. business.
Many of the tools on the market were primarily designed for project management. However, our main focus was clearly on resource management.
Rather than evaluating the tool only on paper, Sulzer GmbH opted for a practical approach to validation with a three-month proof of concept. During this phase, the software was configured to meet Sulzer’s requirements, operated with live data, and tested using specific real-world use cases from day-to-day operations. This meant that a fully functional system was already in place during the trial phase and could be rolled out once it received approval from management.
Seamless Integration into the Existing System Landscape
To reduce manual maintenance and respond more quickly to changes, Meisterplan was fully integrated into Sulzer GmbH’s existing system landscape. The data is automatically updated every morning from three central source systems:
- ERP system: Manages billing and provides project data for creating projects.
- SAP SuccessFactor: As the HR subsystem, it provides employee and master data for capacity planning.
- Time tracking: Transfers actual time worked and time tracking entries directly into the system.
As a result, all relevant project information in Meisterplan is always up to date and consistent, making it easy to answer one key question: Who is working on which project, when, and with how much capacity?
The resulting benefits are particularly evident in day-to-day operations:
When new customer requests come in, we can immediately see who is available and how we can deploy resource effectively. Rotations and rescheduling can also be mapped directly in the system.
Planning follows clearly defined time horizons: short-term planning for operational management of day-to-day activities, medium-term planning for flexible capacity management, and long-term planning for the strategic alignment of resources and skills.

The Right View for Every Stakeholder Level
Different stakeholders benefit from this newly gained transparency in their day-to-day work:
- Executive management uses aggregated KPIs in weekly meetings – such as total revenue across all projects and employee billable utilization – to make strategic decisions.
- Team leads manage their teams operationally in the Team Planner, compare planned and actual utilization, and respond directly to over- or underutilization by reallocating resources.
- Department heads analyze utilization across their entire departments on a weekly basis, identify bottlenecks early, and take targeted corrective action.
- Project managers use customized reports (e.g., to compare planned revenue with actual figures) and, if necessary, they can drill down to the individual employee level to understand and actively manage resource allocationAllocationAllocating describes the strategic process of identifying the correct resources for projects or individual tasks and assigning them accordingly., utilization, and project performance in detail.
Meetings are more efficient today as well. In key steering meetings, such as the project status board, Meisterplan serves as the shared basis for decision-making. Instead of working with static Confluence documents, teams work directly in the system, allowing decisions to be made based on a shared set of data.

Fast Transparency Through Clear Processes
Meisterplan’s successful integrationIntegrationAn integration is a virtual interface that connects different software programs and enables automated data exchange between them. This allows for more efficient processes, better planning, and consistent information. was also made possible through support from management. “The need for a central tool was recognized, and the decision to use Meisterplan was fully supported,” explains Caroline Sauter.
Initial concerns about permissions were also quickly resolved. Thanks to the flexible role and rights system, everyone now sees exactly the data relevant to them without making rights management overly granular.
Meisterplan was also explicitly designated as the central projectProjectA project is a time-limited undertaking with defined objectives and resources that delivers unique results and often includes complex tasks. hub.
“We manage our daily project business with Meisterplan and we always have an overview of the financial and capacity resourcesResourceResources are all the people, places and things that you need to complete projects. The most important resource? Employees, of course!,” says Markus Köster.
This is why Sulzer follows a simple rule: Meisterplan is where the truth lives. Continuous data maintenance improves data quality – and, in turn, confidence in the numbers.
Sulzer’s Conclusion
With Meisterplan, Sulzer GmbH has transformed its resource planning from a labor-intensive, error-prone process into a data-driven and manageable projectProjectA project is a time-limited undertaking with defined objectives and resources that delivers unique results and often includes complex tasks. environment.
Today, transparency is no longer a challenge. Instead, it provides the foundation for fast, informed decisions both in day-to-day operations and at the management level.
- Up-to-date, reliable utilization planning for project managers, team leads, and department heads.
- Flexible resource managementResource ManagementWhen it comes to resource management, the focus is on the optimal planning, coordination and monitoring of resources. The term “resources” includes things like employees, budgets, materials and time. when project demand fluctuates.
- Automatic visibility into key management KPIs, including total revenue, billable utilization, and planned-vs.-actual revenue.
- A single source of truth that keeps all stakeholders better informed.
If Meisterplan were to disappear tomorrow, we would no longer be able to properly track some of the core KPIs we use to manage the entire company. We’re very glad that we implemented Meisterplan.
Read Next
Why Portfolio Unity Doesn’t Require Tool Uniformity
In the fifth post of this series on portfolio planning with Jira data, we look at how organizations can make better portfolio decisions without requiring every team to use the same tool.

Why Annual Planning Alone Isn’t Agile, and Ad-Hoc Decisions Aren’t Either
In the fourth post of this five-part series on portfolio planning with Jira data, we look at why organizations need a regular portfolio decision cadence that balances strategic agility with team focus.